Commercial Solar Panels Ireland (2026)

The SEAI Non-Domestic Microgen Grant for businesses — grant amounts, eligibility, process and real installation costs.

Businesses, schools, community centres and public sector bodies in Ireland can claim the SEAI Non-Domestic Microgen Grant (NDMG) for commercial solar PV — up to €162,600 per installation, covering systems from 1 kWp up to 1,000 kWp. It is the business equivalent of the household solar grant, run by SEAI through its online portal, and works on the same rule: apply for a grant offer before you start any work. Miss that step and you lose the grant.

Commercial solar at a glance (2026):
  • Scheme: SEAI Non-Domestic Microgen Grant (NDMG)
  • Maximum grant: €162,600 (systems ≥1,000 kWp)
  • Eligible sectors: businesses, agriculture, public sector, schools, community centres, non-profits
  • System size range: 1 kWp to 1,000 kWp
  • Apply: mgen.seai.iebefore signing a contract with an installer
  • Installer requirement: must be a Registered SEAI Non-Domestic Microgen (Solar PV) Company

NDMG Grant Amounts by System Size

The grant is calculated per kilowatt peak (kWp) of installed capacity. Below is the full table from the SEAI NDMG page, verified September 2026:

System size Grant value Rate
1 kWp€900€900/kWp
2 kWp€1,800€900/kWp
3 kWp€2,100€700/kWp
4 kWp€2,400€600/kWp
5 kWp€2,400€480/kWp
6 kWp€2,400€400/kWp
7–20 kWp€300/kWp€300/kWp
21–200 kWp€200/kWp€200/kWp
201–1,000 kWp€150/kWp€150/kWp
Over 1,000 kWp€162,600 (max)Grant capped

The step-down in rate at 7 kWp matters for small businesses with a modest roof. A 10 kWp system attracts €3,000 in grant aid (10 × €300), while a 50 kWp system receives €10,000 (50 × €200). At 1,000 kWp the total is €162,600 — and that cap applies to any system above that size too.

Example — a 30 kWp business installation:
  • First 6 kWp at flat-rate: €2,400
  • Remaining 24 kWp at €300/kWp: €7,200
  • Total NDMG grant: €9,600
  • Typical gross install cost at this size: ~€30,000–€45,000
  • Net cost after grant: roughly €20,000–€35,000

Who Can Apply

The scheme is deliberately broad — it covers the whole non-domestic sector:

  • Businesses (SMEs, retail, hospitality, industrial)
  • Agricultural sector (farms with business electricity use — distinct from the TAMS farm grant)
  • Public sector bodies
  • Schools and universities
  • Community centres
  • Non-profit organisations

If you pay commercial electricity rates on a non-domestic tariff, you almost certainly qualify. If you are a farmer looking at panels on farm sheds, see also the TAMS 60% farm solar grant — for some farms, TAMS is the better route; for others, the NDMG is more straightforward. The two are separate schemes with different application portals.

How to Apply

The process has five stages. Stage 3 — ESB Networks connection approval — takes at least four weeks and needs to happen before installation, so the whole process typically runs over two to three months from first contact.

  1. Find a Registered SEAI NDMG Company. Search the SEAI register. Get quotes from at least two or three registered companies before signing anything.
  2. Agree a contract, then apply to SEAI online at mgen.seai.ie. Wait for your letter of offer — which is valid for eight months — before any work starts. This is the step most businesses miss. If you sign a contract and let the installer begin before you have the letter, the grant is gone.
  3. Your installer applies to ESB Networks to connect the system to the grid. Allow at least four weeks (20 working days) for this.
  4. Installation goes ahead once ESB connection is approved.
  5. Installer submits documentation to SEAI. Grant payment follows in four to six weeks once SEAI has received all required paperwork. Delays almost always trace to incomplete documentation — push your installer to upload everything within a few days of completion.
Tax Clearance Certificate. If you receive more than €10,000 in state grants in a calendar year, Revenue requires a Tax Clearance Certificate. Apply via ROS before you hit that threshold — a missing certificate can hold up payment.

Commercial Solar Panel Costs in Ireland

Installation quotes in Ireland vary by system size, roof type, access and the specific equipment specified. Installer-published figures typically range from roughly €1,300 to €1,700 per kWp installed for commercial systems, which puts common business system sizes in the following ballpark:

System size Typical gross cost NDMG grant Estimated net cost
10 kWp (small office)€13,000–€17,000€3,000€10,000–€14,000
30 kWp (medium premises)€39,000–€51,000€9,600€29,400–€41,400
100 kWp (large facility)€100,000–€150,000€22,800€77,200–€127,200
250 kWp (industrial)€250,000–€400,000€49,000€201,000–€351,000

These are rough indicative ranges — get quotes from at least two SEAI-registered companies to price your specific building and usage profile. Flat roofs, asbestos-containing panels, high-rise access, structural surveys and grid upgrade requirements can all push costs higher.

VAT and Tax for Commercial Buyers

Unlike residential solar (which carries 0% VAT in Ireland since May 2023), commercial solar installations are subject to the standard 23% VAT rate. However, VAT-registered businesses can reclaim that VAT in full through their normal VAT return, so the effective net cost for a registered business is the pre-VAT figure after grant. Non-registered entities (some community groups, non-profits) cannot reclaim VAT and should factor the 23% into their net cost calculation.

On the income side, electricity your system exports is treated as a business receipt and taxed as part of trading income. Capital allowances may apply to the installation cost — speak with your accountant on the most tax-efficient structure for your business.

Exporting Surplus Electricity

Once your system is connected to the ESB Networks grid, any surplus power your business generates and does not use on site is exported and paid for under the Clean Export Guarantee (CEG). Every licensed supplier is obliged to offer a CEG rate; as of mid-2026 rates run between 18c and 21c per kWh exported, depending on your supplier. Export payments are straightforward to set up after installation — your installer handles the ESB connection and your supplier registers you for CEG billing.

For businesses with high daytime consumption — a hotel, a manufacturing plant, a large retail unit — the economics of commercial solar are typically strong: the system runs during exactly the hours the business is consuming electricity, so a large share of generation displaces expensive grid power rather than being exported at a lower rate. A payback period of six to nine years is commonly cited for well-sized commercial systems at current electricity prices, though this varies significantly by site.

NDMG vs the Domestic SEAI Solar Grant

SEAI NDMG (commercial) SEAI Domestic Solar Grant
ForBusinesses, public bodies, schools, non-profitsPrivate homeowners
Maximum grant€162,600€1,800
Max system size1,000 kWpNo hard cap on system size
Grant rateSliding scale (€900/kWp down to €150/kWp)Fixed tiers (up to €1,800 for 4+ kWp)
VAT23% (reclaimable for VAT-registered businesses)0% on supply and installation
Apply viamgen.seai.ieSEAI homeowner portal

If you are a homeowner enquiring about solar for your house, see our full SEAI Solar Grant guide and the eligibility rules. The NDMG and the domestic grant are completely separate and cannot be combined for the same premises.

Looking for quotes on a commercial solar installation?

Solar Quotes Ireland connects businesses with SEAI-registered Non-Domestic Microgen installers who understand the NDMG application process. One short form, no obligation, quotes from registered companies.

Get free commercial solar quotes →

Frequently Asked Questions

What is the SEAI grant for commercial solar panels in Ireland? +

The SEAI Non-Domestic Microgen Grant (NDMG) provides financial assistance for businesses, schools, community groups and public sector bodies to install commercial solar PV. The grant ranges from €900 for a 1 kWp system up to a maximum of €162,600. For systems between 7 and 20 kWp, the rate is €300/kWp; from 21 to 200 kWp it is €200/kWp; and from 201 to 1,000 kWp it is €150/kWp.

Can a business get the SEAI solar grant in Ireland? +

Yes — through the Non-Domestic Microgen Grant, not the homeowner scheme. Eligible applicants include businesses, farms, schools, community centres, public sector bodies and non-profits. You must apply through mgen.seai.ie and receive a letter of offer before any installation work starts.

How much do commercial solar panels cost in Ireland? +

Commercial solar panels typically cost in the range of €1,300 to €1,700 per kWp installed, so a 30 kWp system for a medium-sized business would run roughly €39,000 to €51,000 before the NDMG grant. Flat-roof access, structural surveys and grid upgrade requirements can affect costs — always get at least two quotes from SEAI-registered companies.

Is VAT charged on commercial solar panels in Ireland? +

Yes — 23% standard VAT applies to commercial solar installations, unlike residential solar which carries 0% VAT. However, VAT-registered businesses can reclaim the full VAT through their normal VAT return, so the effective net cost is the pre-VAT figure after grant. Community groups or non-profits that are not VAT-registered cannot reclaim it and should factor the 23% into their budget.

Do I need to apply before an installer starts work? +

Yes — this is essential. You must apply to SEAI at mgen.seai.ie and receive your letter of offer before any installation begins. If work starts before you receive the offer, the grant is forfeit. The letter is valid for eight months, so there is no rush to install once you have it — but you cannot work backwards from a completed install.

Can commercial solar panels export electricity in Ireland? +

Yes. Once connected to ESB Networks, any surplus electricity your system generates is exported and paid for under the Clean Export Guarantee (CEG). Every licensed supplier must offer a CEG rate; current rates run roughly 18c to 21c per kWh exported. Export payments are taxable business income.

Published: 8 September 2026. The SEAI NDMG grant table (grant values per kWp tier from €900 at 1 kWp to a maximum of €162,600, the 1,000 kWp system cap, eligible applicant types, and the five-stage application process) is confirmed against the live SEAI Non-Domestic Microgen Grant page (seai.ie/grants/business-grants/commercial-solar-pv), September 2026. Commercial installation cost ranges are indicative figures drawn from installer-published data and should be verified with SEAI-registered companies. VAT rules confirmed against Revenue.ie; CEG rates are current at time of publication but vary by supplier.